41.6 F
Muscatine
Thursday, May 6, 2021
More

    Delayed pavement maintenance programs begin October 19

    City of Muscatine
    City of Muscatinehttps://www.muscatineiowa.gov
    This content has been provided by the City of Muscatine via press release or other notification systems to Discover Muscatine. It is being re-published as a resource for the Muscatine community. All questions regarding this content should be directed to the City of Muscatine at 215 E Sycamore St or (563)264-1550

    Muscatine Living

    Moving with Kids

    Whoever said moving with kids is easy was a liar. I said what I said. Families with children that...

    Living History: Shirley Welker

    MUSCATINE, Iowa--Born and raised in Muscatine, Shirley Welker has always loved the town she calls home. From the time...

    Mission Pawsible May 5

    Adopt Blackie! Breed: Male, black, domestic short hair Age: Three-years-old A quiet cat, Blackie likes to spend time in calm and private...

    MUSCATINE, Iowa – Full depth patching on Cedar Street and replacement of the asphalt pavement on a portion of Leroy Street are scheduled to begin next week according to the City of Muscatine Public Works Department.

     

    The 2020 Full Depth Patching Program along with the 2020 Asphalt Street Overlay Program were both put on hold last Spring as the City of Muscatine assessed the financial impact of the COVID-19 health crisis. With better than anticipated revenues from the Road Use Tax, several “high priority” projects were given the go-ahead by the Muscatine City Council on October 1, 2020.

     

    Both programs will be mobilized starting on Monday, October 19, 2020, with Leroy Street closed from Mulberry Avenue to Amherst Avenue for the asphalt overlay project. Lane restrictions will be put in place on Cedar Street on Monday between Muscatine High School and the Cedar Street roundabout for the full depth patching.

     

    “Due to better than anticipated Road Use Tax revenues, funds are available to be used for roadway maintenance projects,” Brian Stineman, Public Works Director, said.

     

    101220 Leroy Street 001 (JPG)Public Works identified sections of Cedar Street, Ford Avenue, and Evans Street as high priority concrete streets in need of immediate repair. Heuer Construction, Inc., was the low bidder for the project at $47,710.00. In addition, Public Works identified Leroy Street as high priority asphalt street in need of immediate repair. Taylor Ridge Construction was the low bidder for the project at $43,500.00.

     

    Cedar Street will be reduced from three-lanes to two-lanes through the work area. Drivers are urged to be alert, watch for construction workers, and to obey traffic control signage. Once Cedar Street is completed, Heuer Construction will move to Ford Avenue. If funds remain and weather permits a section on Evans Street will be repaired before the winter shutdown.

     

    Milling of Leroy Street is set to begin on Monday, weather permitting, with the asphalt overlay to follow.

    Latest News

    Kent Stein west concession, rest rooms closed tonight (May 5)

    MUSCATINE, Iowa – The Muscatine Parks and Recreation Department wishes to inform the public that there will be no restroom...

    Get Discover Muscatine in Your Inbox

    More Articles Like This