    Questions answered during WHSSP public meeting Wednesday

    City of Muscatinehttps://www.muscatineiowa.gov
    This content has been provided by the City of Muscatine via press release or other notification systems to Discover Muscatine. It is being re-published as a resource for the Muscatine community. All questions regarding this content should be directed to the City of Muscatine at 215 E Sycamore St or (563)264-1550

    Muscatine Living

    MUSCATINE, Iowa – The City of Muscatine hosted a public meeting on Phase V of the West Hill Area Sanitary and Storm Sewer Separation Project (WHSSP) Wednesday (April 21) with several residents from the area of the 2021 construction in attendance in person and online.

     

    The main focus of the meeting was to introduce the contractor, present a brief overview and a tentative schedule of the project, and answer questions from residents who live in the area affected by the construction.

     

    Hagerty Earthworks, Inc., was awarded the $6.03 million contract for Phase V of the WHSSP during the April 1 City Council meeting. This phase includes replacing sewers on West 8th Street from Broadway to Lucas, on Climer Street from West 8th Street to Lucas, Logan Street from Lucas to Climer, Lucas Street from 912 Lucas to Fletcher Avenue, and through the ravine between Climer and Lucas. 

     

    The first year of the two-year project will focus on West 8th Street and Climer Street.

     

    Work on Phase 5A (2021 construction season) is tentatively scheduled to begin on Monday, May 3 on the property at 891 West 8th Street. The City of Muscatine purchased the property earlier this year. The house was moved away from its foundation on April 1 to facilitate the separation of the combined storm sewer that runs from West 8th Street through the property. The City plans to have a new foundation built, replace the home, and sell the property once the construction work is completed in the area.

     

    The tentative schedule indicates that work on West 8th Street will begin on May 24 and be completed by July 30. The rest of the construction season will include work on Climer from West 8th to Lucas.

     

    Most of the questions Wednesday night came from residents on Climer Street who were concerned about access to their homes during the project, and how much of the sidewalk would be replaced. City officials and the contractor indicated that work on Climer would not start until July 30 or after, and that they would be in contact with homeowners as the work progresses.

     

    An access road will be added to the boulevard on certain sections of Climer Street for residents who do not have alley access. Accommodations are also available for those with special needs by contacting Public Works at 563-263-8933.

    ­­­­­

     

    Drivers are reminded to slow down and use caution when travelling through the construction zone, obey traffic control devices, and be aware of workers. Use an alternate route if possible.

     

    For more information on City of Muscatine construction projects click on CONSTRUCTION to visit the Department of Public Works Construction Projects page.

     

    If you have a comment or concern, please email [email protected] or [email protected]. A staff member will respond within 24 hours.

     

     

     

     

     

     

     

     

    WHSSP Phase 5A Tentative Schedule

     

    Task

    Tentative

    Start Date

    Tentative

    End Date

    Phase 5A1.5

    Utilities at 891 West 8th Street

    May 03, 2021

    May 21, 2021

    Phase 5A.1

    Utilities on West 8th from Climer to Lucas

    May 24, 2021

    July 16, 2021

    Paving & Grading on West 8th from Climer to Lucas

    June 21, 2021

    July 30, 2021

    Phase 5A.2

    Utilities Climer Alley

    July 19, 2021

    July 30, 2021

    Paving Climer Alley 

    August 02, 2021

    August 06, 2021

    Phase 5A.3

    Utilities east half of Climer Street

    August 02, 2021

    September 24, 2021

    Paving east half of Climer Street

    September 06, 2021

    October 01, 2021

    Phase 5A.4

    Utilities west half of Climer Street

    September 27, 2021

    October 29, 2021

    Paving west half of Climer Street

    October 11, 2021

    October 29, 2021

     

    Latest News

    Long agenda awaits City Council during August 5 meeting

    MUSCATINE, Iowa – A lengthy list of action items await the members of the Muscatine City Council when they meet...

    Get Discover Muscatine in Your Inbox

    More Articles Like This