Weather does not slow down local construction projects
by City of Muscatine
November 16, 2020

MUSCATINE, Iowa – Two spring snowfalls have not halted work on construction projects in Muscatine. Taking advantage of reduced traffic and business restrictions due to local, state, and federal COVID-19 guidelines, contractors are picking up the pace especially in Downtown Muscatine.

Work on the 2nd Street Streetscape Project began on Monday (April 13) in the block from Cedar to Walnut streets. This block has the most work to be accomplished during the two-year project and includes replacement of a collapsing sanitary sewer line, curb-to-curb pavement restoration, and replacement of sidewalks on both sides of the block.

041720 Second Street No Meeting Notice (JPG) The extent of the work necessitated the full closure of the 300 block of East 2nd Street, but this is the only one of the six stages that will see a full closure during construction. Each block of the project is assigned a stage and each side designated either “A” or “B” with work on one side of a block completed before the opposing side is started. The current work is being conducted in Stage 5.

City staff has been meeting with local business owners over the past year and had plans to host weekly block meetings with residents and business owners during construction. However, due to the COVID-19 outbreak those meetings have been cancelled until further notice. Residents or business owners who have questions about the project, the schedule of work, or would just like more information about the project can contact Bill Haag, Construction Project Manager, at (563) 299-0690.

Currently, 2nd Street is closed from the intersection with Cedar Street to just west of the intersection with Walnut. Cedar is also closed from the #2 Alley to the intersection with 2nd Street. The contractor will start pavement restoration for that block once the sewer has been replaced. After the block is opened, work will begin to replace the sidewalks on each side, one side at a time to allow customer access to the businesses on the block.

Work is expected to be completed by the end of May.

The next stage to be worked on will either be Stage 6 (Walnut to Mulberry) or Stage 4 (Sycamore to Cedar) depending on the progress of the Mulberry and 2nd Street roundabout. There is some sewer replacement work and pavement replacement in Stage 6.

The 2nd Street Project is comprised of sidewalk, roadway, utility, and streetscape construction on 2nd Street from Mulberry Avenue to Pine Street. Construction primarily includes pavement removal, excavation, concrete sidewalks, concrete roadway paving, underground utility improvements, concrete pavers, and streetscape amenities.

The Muscatine City Council awarded the $2.9 million contract for the 2nd Street Streetscape Project to KE Flatwork, Inc., of Elbridge, Iowa, at the February 6, 2020, City Council meeting. KE Flatwork, Inc., was the lowest of four bidders for the two-year project.

Additional information can be found on the 2nd Street Streetscape Project page on the City of Muscatine website.

Mulberry-2nd Street Roundabout

Underground work on the Mulberry Avenue-2nd Street Roundabout Project has been completed with the contractor working on grading the new intersection before the area is proof rolled and rock added. Pavement restoration is tentatively scheduled to begin in later this month with the project wrapping up by the end of May, depending on the weather.

Mulberry Avenue is currently closed from the #1 Alley to 3rd Street and 2nd Street is closed from Mulberry Avenue to Orange Street. Eastbound traffic on Mississippi Drive is detoured at Iowa Avenue to 5th Street to Park Avenue. The detour will remain in effect until the project is completed.

Houser-Cedar intersection

Pavement restoration of the Houser and Cedar intersection has been completed with the contractor scheduled to seal the joints Monday (April 20) before opening up the intersection by the end of the day on Monday. The work was originally scheduled to be included in the 2020 Full Depth Patch contract but was moved up due to the reduced traffic and school closure associated with the COVID-19 outbreak. Work in the intersection began March 31.

The 2019 Full Depth Patching Project included work on North Houser Street, South Houser Street, University Drive, Lake Park Boulevard, and several “emergency” patches at various locations throughout Muscatine.

The 2020 projects will be sent out for bid later this spring. The Full Depth Patch project will be smaller than this past year as the city will focus on hot mix asphalt overlays of a number of street sections and alleys in 2020.

West Side Trail

Heuer Construction has completed the West Side Trail project concrete work from Hershey to Crossroads, Inc., with only a section running through the Arbor Commons development yet to be competed. The contractor is currently focusing on backfilling, hydro seeding, and finishing landscaping along the completed trail from Hershey to Crossroads, Inc.

The trail through the Arbor Commons subdivision will be completed once pavement work in that development has been completed.

West Hill Sewer Separation Phase 4C

Phase 4C of the West Hill Sanitary and Storm Sewer Separation Project (WHSSSSP) began March 16 with underground work for the first stage (Iowa Avenue from 8th to 9th Street and 9th Street from Iowa Avenue to Chestnut Street) completed. Several individual resident water services were to be connected in the next week before pavement restoration begins. Once this work is done, the contract will move to the second stage starting at Linn and 8th Street and working toward Broadway.

Sewer separation and pavement restoration work will also be undertaken on Maiden Lane and Roscoe Avenue, Linn Street from 7th to 8th Street, and on 8th Street from Linn to Broadway. The detour for Phase 4C will be implemented once work begins on 8th Street with regular traffic detoured to 7th Street from Cedar to Broadway. The 7th Street detour will be modified once underground work reaches the Broadway intersection on 8th Street.

Park Avenue Three Lane Conversion Project

The Park Avenue Four-to-Three Lane Conversion Project is scheduled for the 2020 construction year with a public hearing scheduled May 7 Muscatine City Council meeting. The project will convert Park Avenue from four-lanes to three (two traffic lanes with a center turn lane) from Harrison Street to the Mad Creek bridge. A June 16, 2020, bid letting is planned by the State of Iow. No detours are planned during the work but there will be lane restrictions.

Alley Asphalt Overlay Project

The 2019-2020 Alley Asphalt Overlay Project will begin once the asphalt plants reopen for the 2020 construction season. A total of 11 alley segments are on the list for asphalt overlay. The proposed alleys are: 400 block of Busch Street; Grover and Charles (New Hampshire to Hershey); Salvation Army at Oregon and Illinois (Earl to Baker); Bond and Bleeker (Grandview to Liberty); Iowa and Sycamore (East 9th to East 10th along with East 10th to East 11th); Taylor and Clinton (New Hampshire to Hershey); Hawthorne and Washington (Orchard to Park); Hagerman and Lorenz (Terrace Heights to Roscoe); 4th Street Park alley (Locust between 3rd and 4th streets); and Pine and Linn (3rd to 4th streets). Plans for the 2020-2021 Alley Asphalt Overlay Project and the 2020-2021 Street Asphalt Overlay Project are being developed and should go out for bid later this Spring.

Spring flooding

The Mississippi River crested at 18.93 feet on April 11 and is expected to continue a steady fall over the next several weeks and receding below flood stage (16-feet) by April 24. The river is currently at 18.1 feet and has been above flood stage since March 24.

On April 17, 2019, the river was at 20.32 feet. It was during 2019 that the river surpassed flood stage on March 16 and spent the next 99 consecutive days above flood state (16-feet), a record for Muscatine.

Recent Stories

Recent Shows

Get Discover Muscatine in Your Inbox

Select list(s):
en_USEnglish